SAMU merging units, IEC 61850
SAMU merging units convert analog signals of conventional CTs and VTs into IEC 61850 digital streams for the process bus of a digital substation. The output is Sampled Values per IEC 61869-9 / IEC 61850-9-2LE.
- Version
- 19-inch for the substation building; compact for the switchyard
- Output
- Sampled Values IEC 61869-9 / IEC 61850-9-2LE
- Synchronization
- 1PPS, IEEE 1588
- Redundancy
- PRP, HSR
Price, availability and lead time on request. We help with analogue selection, customs clearance and delivery.
Description
A 19-inch version is available for the substation building, and a compact version for the switchyard. Time synchronization is done via 1PPS or IEEE 1588. Network redundancy is supported through PRP and HSR. This allows existing instrument transformers to be connected to a digital substation without replacing them.
Technical specifications
| Version | 19-inch for the substation building; compact for the switchyard |
|---|---|
| Output | Sampled Values IEC 61869-9 / IEC 61850-9-2LE |
| Synchronization | 1PPS, IEEE 1588 |
| Redundancy | PRP, HSR |
Request a price and lead time
SAMU merging units, IEC 61850. We reply within one business day.
Or email sales@usk.ua or call 044 339-50-20.
Customs codes
| UKTZED (Ukraine) | 8537 10 98 90 |
|---|---|
| HS, 6 digits | 8537 10 |
| CN (EU) | 8537 10 98 |
| HTSUS (USA) | 8537 10 91 70 |
| China customs tariff | 8537 10 90 90 |
Codes are for reference: the final code is determined at declaration for the specific model.
Questions and answers
In what format does the SAMU output data?
Sampled Values per IEC 61869-9 / IEC 61850-9-2LE.
How is time synchronized?
By a 1PPS signal or by the IEEE 1588 protocol.
Is there a version for installation in the switchyard?
Yes, in addition to the 19-inch version for the building there is a compact one for the switchyard.
Similar equipment from other manufacturers